The construction of MMTP wrapped up on April 16, 2020 at 9pm. All of the towers are up and the last line has been strung. Some work remains like fixing deficiencies, cleaning up, and energizing before the anticipated in-service date of June 1, 2020.
The monitors have been working on final inspections of spill clean up, picking up small pieces of garbage and debris left behind and taking note of larger debris items that will need to be picked up later on. Much of the remaining clean up will be done in June once ground conditions have dried up.
For the rest of this month, the monitors are working on writing individual report cards and a final report for the Project, setting up monitoring sites, and developing a re-vegetation plan.